Covenant Building Project Update

Covenant Building Project Update

Covenant Building Project Update

As of this writing, ATT is making progress on the new church tower on the Kingswood building that will conceal all the electronics of the new cell tower. New steel is being attached to the existing structural steel that supports the roof. This will be used to secure the tower to the building.

Additional good news to share is that the first three months of rent has been received and should be on track to arrive each month.

The permits for the elevator and other renovations have been applied for and are winding their way through the system. We are hoping to break ground in early February. The first thing scheduled is digging the foundation for the new elevator; if the weather is unfavorable for digging, work will begin on the inside of the building.

This article can be found in the February 2019 Newsletter.